Port Otago Limited has commenced a $45 million capital works programme that will position it commercially for the next generation. The infrastructural works programme, ‘Next Generation Port Otago’ will allow larger ships to access Port Chalmers while bolstering the port’s service offering to exporters. Read the overview »

01.08.2013
Full consent for Next Generation Project granted
/assets/
01.05.2015
Shipping channel deepening commences
/assets/
01.07.2015
Container wharf No.1 Sheet Piling commences
/assets/
01.07.2015
Back Beach warehouse expansion begins
/assets/
01.08.2015
Sawyers Bay warehouse construction begins
/assets/
01.10.2015
Container wharf No.1 Sheet Piling completion
/assets/
01.12.2015
Back Beach warehouse expansion completion
/assets/
01.12.2015
Shipping channel at 13.5m
/assets/
01.03.2016
Sawyers Bay warehouse completion
/assets/
01.12.2016
Shipping channel at 14m
/assets/

Project Updates

Building a Sustainable Primary Deep-water Port